A tenant improvement is interior construction that takes a base-building shell to a finished condition a particular occupant can use. People also call that work a tenant build-out or a commercial fit-out. The lease, occupancy agreement, or owner’s project defines who designs it, who builds it, and which costs any allowance funds. The improvement is not the structure, the building permit, or the accessible path of travel.
The fit-out, the base building, the permit, and the accessible path of travel are separate assignments, and an allowance funds only the costs the agreement actually names.
Finishes that make a shell usable
In the U.S. General Services Administration Pricing Desk Guide, 5th edition, effective August 1, 2020, tenant improvements are the finishes and fixtures that take space from shell condition to a finished, usable condition. The guide says the space is then complete, meets applicable building codes, and meets the agency’s functional needs. As of November 2026, 41 CFR 102-71.50 states that rent is set in accordance with that guide. The former subpart that spelled the allowance out section by section is no longer the current eCFR text.
That definition prices space GSA controls. The guide says commercial practice also separates shell from tenant work, and that the shell wording is not a prescription for a private lessor’s design. Cold shell, warm shell, and vanilla box are nicknames, not a code. Use an itemized delivery condition.
The guide’s typical list includes partitions, doors and hardware, millwork, wiring and outlets to the core, telephone and data outlets, and in-suite fire-alarm devices and exit signs. A building standard is not shell. A required door type or carpet color still limits choice. It does not move the item into the shell.
Who owns the work
Ownership is several jobs: approving the layout, drawing it, hiring trades, paying, accepting the work, and keeping the base building afterward. A lease can split them. A school district that renovates a wing it owns has no landlord, and its capital budget replaces an allowance.
None of the usual landlord-tenant patterns is a legal default. The landlord’s contractor may build to an exhibit while the tenant approves changes. The tenant may hire the team while the landlord approves drawings and any work on base systems. Or the parties may split at a written point, such as base air and power to a panel, with distribution inside the suite on the tenant side.
GSA customer guidance updated February 3, 2026, describes a federal version of that split. Rent covers core and shell, meaning the structure and common amenities, plus an allowance for the build-out. Work past the allowance needs its own authorization, with a scope, an estimate, identified funds, and a signature, before GSA accepts it. That page is for GSA customers, not a private office or a county school. Substantial completion, the code official’s sign-off, and lease commencement are different dates.
What an allowance does not include
An allowance is a funding source, not the work itself. In the Pricing Desk Guide it has a general component for ordinary office finish and a customization component for that occupant’s special items. The guide states no single private-market price, and this page states no allowance amounts.
Shell sits outside the allowance: the enveloping structure, base building systems, and finished common areas beside the occupant space. Separate security capital is outside both shell and tenant improvement. Work above the cap is outside the allowance too. Where a lessor provides the allowance, the guide charges planning, design, construction management, labor, materials, general conditions, overhead, and contractor profit against the cap.
Demolition of a prior build-out is not automatically included. For vacant Public Buildings Service space, the guide does not charge that demolition to the new customer’s allowance. A private work letter can do the opposite. On a phased job, the guide allocates the allowance among the phases so early work does not spend the whole cap without a recorded decision.
A private allowance excludes whatever the work letter omits. Furniture, moving, signage, and communications gear are frequent fights, not a national exclusion list. Unused funds are not a rent reduction unless the lease says so. The allowance also does not repair base systems the landlord kept, obtain the permit, or build a path of travel outside the exhibit.
Why the base building stays separate
The base building is the part the occupant did not come to redesign: structure, envelope, shared shafts, main electrical and mechanical plant, and common areas that serve more than one tenant. The Pricing Desk Guide puts those items in shell. Customer-driven upgrades, such as more cooling, another elevator, higher floor loading, or lighting past the building standard, are tenant improvements charged to the allowance even when the equipment sits in a shared room.
Condition is not capacity. A running air handler can lack spare capacity for added rooms. Write the interface down: where the main duct stops, whether the floor restrooms are shell, who owns the fire-alarm panel, and what structural reserve exists.
An owner-occupant has the same split inside one budget. A school that re-partitions a wing still depends on boilers, switchgear, and a roof that were not part of the room refresh. Soleil Energy’s power work is medium- and high-voltage distribution, a different scope from suite finishes. A new roof opening, or a later solar array, is not an interior finish. Replacing a roof before adding solar is its own decision.
Why the permit path is separate
A building permit is permission from the authority having jurisdiction. It is not a lease clause, and an allowance does not apply for it.
The 2024 International Existing Building Code is a model. Its administration chapter says the code is meant to be adopted and is not effective without enforcement. As of November 2026, the model text requires the owner, or the owner’s authorized agent, to obtain a permit before repairing, altering, relocating, demolishing, or changing occupancy, and before altering a regulated electrical, gas, mechanical, or plumbing system.
The same chapter exempts some work, including painting, papering, tiling, carpeting, cabinets, counter tops, and similar finish work, plus narrow tasks such as replacing lamps. An exemption is not permission to violate the code or other laws. The model text also limits the height of some nonfixed partitions. This page does not treat that figure, or any model dimension, as a design rule. Maryland, Northern Virginia, and the District of Columbia adopt and amend codes on their own. As of November 2026, this page does not name the edition in force at a given address.
The permit stays separate because a tenant is not automatically the owner’s agent. Carpet can sit on a model exemption list while new full-height partitions do not. A passed inspection does not show that spending against the allowance was eligible. A qualified professional must assess the actual space before anyone treats the work as exempt.
Why the accessible path is separate
Accessibility law asks a different question from the permit list. For places of public accommodation and commercial facilities, 28 CFR 36.402, current on the eCFR as of November 19, 2026, and checked November 22, 2026, treats an alteration as a change that affects or could affect usability. Remodeling and changes to full-height partitions count. Painting and ordinary mechanical or electrical changes do not, unless they affect usability. A model permit exemption does not answer that test.
When an alteration affects a primary function area, 28 CFR 36.403 requires the path of travel to that area, including serving restrooms, telephones, and drinking fountains, to be accessible to the maximum extent feasible unless cost and scope are disproportionate. A primary function is a major activity the facility is intended for. Offices and other work areas count. Mechanical rooms, corridors, entrances, and restrooms do not. Restrooms remain on the path when they serve the altered area, with the route from the sidewalk and the entrance. The Access Board scoping chapter states the same duty, so the path can leave the suite.
This page states no access dimensions. Section 36.403 says path work is disproportionate when the cost exceeds 20% of the cost of the alteration to the primary function area. The 2010 Standards compilation states that same 20% comparison for Title II public entities in 28 CFR 35.151. If the whole path would pass that line, work still follows a priority: an entrance, a route, a restroom, telephones, drinking fountains, then other elements such as parking, storage, and alarms.
If the tenant alters only space it occupies, Title III does not by itself assign unaltered landlord areas to that path duty. The lease can still assign the cost. A district-owned school uses Title II instead. Splitting one job into small pieces does not avoid the duty. A later alteration within three years pulls earlier costs into the test: Title III counts work after January 26, 1992, and Title II counts work on or after March 15, 2011. Elements a private entity already built to the 1991 Standards need not be rebuilt solely because a served primary function area is altered later. Title II’s safe harbor on the ADA.gov compilation uses the 1991 Standards or the Uniform Federal Accessibility Standards for work before March 15, 2012. This page does not decide a particular wing.
Systems the fit-out can disturb
Record where new circuits and ducts connect, and what the base systems can still supply.
Enclosure performance is a different specification. Unified Facilities Guide Specifications section 01 91 19, dated May 2023, covers building enclosure commissioning for new construction and major renovations that upgrade the envelope, used with a separate building-commissioning section. An interior re-partition that leaves the enclosure alone is outside that scope. If the enclosure is cut, those tests stay off the finish punch list. The federal section is not automatic language in a school contract or a private lease.
ENERGY STAR Portfolio Manager compares energy use with similar buildings, past use, or a reference level. Where a 1 to 100 score exists, it is normalized for weather and operations, and a score of 50 is the median. Updating floor area or hours does not close a permit or fund an allowance.
For occupied work, name which stairs and restrooms stay open. A temporary barrier is not the accessible route in the regulations. The code official sees that note when the permit requires it.
An illustrative occupied reconfiguration
This example is illustrative. It is not a Soleil Energy project, and it uses no prices or dimensions.
A nonprofit leases one floor. The work letter lets the landlord’s contractor build only an approved drawing, up to an allowance the lease defines, and the tenant hires the designer. The tenant wants tutoring rooms instead of an open office. The air handler, electrical room, and restrooms sit outside the suite.
The drawing adds full-height partitions, room power, and a diffuser change. The air handler stays base building unless the work letter is amended. The partitions are the tenant improvement. The permit is separate: as of November 2026, the code official decides the adopted code. The lobby route and restrooms are a path question because the offices are a primary function under the Title III examples. The landlord is not automatically assigned that unaltered path, and the lease is silent, so they write the assignment before construction. A qualified professional makes that call on a real floor.
Allowance draws, permit comments, and a valve leak outside the suite stay on separate lists. If a district owned the rooms, the allowance would drop away and Title II would be the path question, while cooling, the permit, and the route would stay separate.
What to settle before anyone prices the job
| Decision | Write this down | Why it stays separate |
|---|---|---|
| Delivery condition | Itemized base scope, not a nickname | Nicknames hide ducts, panels, and restrooms |
| Allowance | Eligible costs, the cap, unused funds | A cap does not describe or fund omissions |
| Above the cap | Who may add cost before it is built | Extra work needs its own authority to spend |
| System interface | Where air, power, plumbing, and alarms stop | Capacity is not a finish choice |
| Permit | Applicant, adopted edition, claimed exemption | The code official decides, not the lease |
| Access path | Primary function, route, serving restrooms | The path can sit outside the suite |
| Occupied use | Exits and rooms that stay open, plus hours | A finish schedule does not run the building |
| Closeout | As-builts, inspections, allowance log | Mixing the files hides the open item |
The table is a briefing agenda. It does not replace the adopted code or the signed lease.
Frequently asked questions
Does the allowance pay for whatever the space needs?
No. It funds the defined build-out. Shell, separate security capital, and costs past the cap sit outside the federal source. A private work letter is the controlling list. A later base-system repair is new scope unless that document already included it.
If the tenant builds only inside the suite, who fixes the route?
Not automatically. Title III leaves unaltered landlord areas off the path duty created by work inside space only the tenant occupies. The entrance and serving restrooms can still be on the path, and the lease may assign the cost. A public owner confirms Title II.
Are paint and carpet outside both the permit and the access rules?
No single rule covers both. The 2024 model code exempts some finishes from a permit and says that is not permission to break other laws. Title III treats painting as an alteration only if it affects usability, and it treats new full-height partitions as alterations. As of November 2026, confirm the adopted code in Maryland, Northern Virginia, or the District of Columbia.
Should enclosure commissioning be in every fit-out?
No. The May 2023 section applies to new construction and major renovations that upgrade the envelope, beside a separate building-commissioning section. Use it when the enclosure changes. Leave it out of an interior-only fit-out. A qualified professional matches the specification to the work.
Will an energy score show that the build-out worked?
It can compare measured use after the inputs are updated. It does not show that partitions, alarms, or restrooms meet the drawings, the lease, or an accessibility standard.
Plan the interfaces before the build
Price the finish scope, the base building, the permit, and the access path as separate assignments that share one calendar.
Soleil Energy’s construction work includes commercial and institutional renovations, tenant build-outs, and phased work in occupied schools and government buildings. Published coverage names Maryland, Northern Virginia, and Washington, DC, with counties listed on the service-area page. Confirm an address that is off that list before assuming a crew can take the job. For a phased look at an occupied suite, bring the records above to Soleil Energy’s construction team. A qualified professional must assess the actual space before scope, code, or access conclusions are treated as settled.